Canals : Canal Construction An advance of 60m per day was achieved during the construction of this 1300m canal. Top : GaMabintane, Limpopo, South Africa - Client : Africare SA - Designed and built by Dams for Africa, November 2002 |
| Next Canal | Back to main Canal page | Back to Home page |
(1) Shutters are installed in the trench after it has been dug to the correct width and gradient. | (2) Base concrete is placed in the trench to a predetermined height. |
|
(3) Profiled sheets made from fibre reinforced mortar are installed in the trench. |
(4) The profiled sheets are encased in concrete. |
|